Foundation Schools Construction in Nadu - Nedu Phase 2 - Guidelines Mana Badi Nadu Nedu - Foundation Schools Construction in Nadu - Nedu Phase-II - Guidelines to take up basic infrastructure works with Nadu Nedu components for improving Infrastructure facilities in Anganwadi Buildings and construction of new Anganwadi Buildings - Implementation of the program through Foundation School Development committees through Community Contracting Guidelines for implementation of the program - Orders
Circular No.1794016/MBNN/2022 Dt. 26.07.2022
Sub: Mana Badi Nadu Nedu - Foundation Schools Construction in Nadu - Nedu Phase-II - Guidelines to take up basic infrastructure works with Nadu Nedu components for improving Infrastructure facilities in Anganwadi Buildings and construction of new Anganwadi Buildings - Implementation of the program through Foundation School Development committees through Community Contracting Guidelines for implementation of the program - Orders Issued - Regarding
Government has taken a decision to give a facelift to all the Government Schools including Foundation Schools and Satellite Foundation Schools (Anganwadi Centres) in the State by improving the infrastructure to provide quality education including pre-primary education.
Government decided to
1. Construct new AWCS for the building-less AWCS outside primary Schools.
II. Construct new AWCS for the centres located in the school premises.
III. Up gradation of AWCS located in School premises under Nadu-Nedu Phase-II.
Government vide G.O. No.84, dated 24.12.2021 has introduced certain changes in the Education system where in PP1, and PP2 are introduced as part of the primary education. As they are now part of the Education system Infrastructure improvements are proposed under Phase -II of Mana Badi Nadu-Nedu Program. (4) Director Women and Child Welfare department has given the list of the AWCs to be taken up in consultation with District collectors for both upgradation and for new construction.
For the implementation of the program the following orders and guidelines are issued.
Unit cost for construction of Foundation Schools:
a) Satellite Foundation School Building
b) Class rooms for Pre - Primary (AWC) in co - located Foundation Schools.
Implementing agencies:
Role of Foundation School Development Committee and Parents Committee:
Process:
Role of Sachivalyam Engineering assistant / Amenities Secretary:
Nadu - Nedu Photos:
Provisions in the Estimates:
Administrative and technical sanctions:
Building Plan and Orientation:
a. Outside the School Campus (Satellite Foundation School):
b. Inside the School Campus (Co-located Foundation School):
Fund flow:
Convergence and role of various departments:
Time Schedule for the program:
Central Procurement Materials: